Reconstruction to resume on Scotland Main Street

Facebook
Twitter
LinkedIn

​HARRISBURG – The Pennsylvania Department of Transportation will resume a nearly 1.5-mile reconstruction project on Main Street in the Village of Scotland, Greene Township, this week.

Weather permitting, southbound Main Street will be closed on Tuesday, March 1, between Woodstock Road and Scotland Avenue as part of the third phase of this multiple phase project.

A detour will be in place using Route 997.

Northbound traffic will be maintained through the work zone using long term traffic control.

This project consists of base repairs, drainage installation, resurfacing, reconstruction, curb and sidewalk installation, box culvert installation, and other miscellaneous construction the entire length of Main Street, which intersects at either end with Route 997.

Work is expected to be completed by October 2022.

Cottles Asphalt Maintenance, of New Cumberland, PA, is the prime contractor on this $4,479,265.53 project.

Motorists can check conditions on major roadways by visiting 511PA. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras.

Are you enjoying local news?

First Month 99¢

Already a subscriber? Login here.