WAYNESBORO, Pa. — The Pennsylvania Department of Transportation (PennDOT) announced that on Wednesday, Nov. 18, the contractor plans to open the new roundabouts on Route 997 (Anthony Highway) in their final configuration near Waynesboro Borough in Washington Township.
Weather permitting, the contractor will work on Monday, Nov. 16, and Tuesday, Nov. 17, each day painting lines and installing pavement markings on Route 997, Orchard Road (Route 2015), and Washington Township Boulevard within the project corridor.
Lane restrictions will be in place during daylight work hours. Travelers should be alert for single-lane restrictions with flaggers directing traffic through the work zone.
On Wednesday, Nov. 18, the contractor plans to open both roundabouts in their final configuration as well as opening the Orchard Road connection to the southern roundabout and the Washington Township Boulevard connection to the northern roundabout.
There will be lane restrictions under flagging while the shift is being implemented. Access to businesses and residences will always be maintained, PennDOT officials said.
This project includes the construction of two new roundabouts on Route 997. The first is located at the intersection of Orchard Road and the second is located just to the north at the new connection of Route 997 and Washington Township Boulevard.
This project also consists of road widening, curb ramps, drainage improvements, stormwater management and new lighting.
Mitchell Knorr Contracting, of Bloomsburg, Pennsylvania, is the contractor on this $6,244,217 project.