BOONSBORO, Md. – Despite a substantial improvement in Boonsboro’s water supply following the completion of a new reservoir in August, the town’s Municipal Utilities Commission voted this week to postpone a decision on water and sewer capacity for 53 proposed homes in the Dean North development, citing continued uncertainty about the town’s water supply and aging infrastructure.
Commissioners agreed to gather more information before reconsidering the request, possibly in January. The developer has not yet received subdivision or site-plan approval from the town’s Planning Commission.
Officials estimate that the old reservoir was losing 80,000 to 100,000 gallons of water daily through leaks, a problem the replacement has largely eliminated. But the town’s official capacity calculations still reflect years of excessive water losses.
Those calculations, based on a five-year average of water consumption from 2021 through 2025, show a deficit in available capacity. Because the new reservoir began operating only three months ago, its benefits will take years to be fully reflected in the calculations.
Officials said additional operating data is necessary to determine how much water the town can reliably provide. They also want engineering estimates for improvements to pumping equipment and water lines that might become necessary to serve additional development.
The town’s sewer treatment plant has ample unused capacity, operating at approximately 30 to 35 percent of capacity. Water treatment and distribution present the greater obstacles.
The discussion also exposed frustration over whether residential development like the Dean North proposal generates enough revenue to maintain the infrastructure it requires.
“More houses ain’t going to bring more money. And I rest my case,” a public works employee said, arguing that previous developments had added to the town’s maintenance burden without providing sufficient money for repairs.
Commissioners discussed whether developers should pay for improvements directly related to their projects and whether existing utility customers should contribute to broader infrastructure upgrades through a capital improvement fee.
No fee was proposed for adoption.
Town Manager Rachel Souders said she will compile a list of long-standing infrastructure needs, estimate their costs and establish priorities as the town prepares its next budget. She also expects to hold additional budget workshops to explain the projects and their costs to residents.
The commission unanimously approved a motion to postpone the development’s capacity request until it has enough information to make an informed decision.
The delay leaves the developer waiting while Boonsboro determines how much additional growth its water system can support.